Photo courtesy of City of Taylor
The Taylor City Council will consider a proposed development agreement for Taylor Technology Campus, formerly known as Project Mustang, during its Oct. 8 meeting.
The 664-acre project, proposed by Big Watt Digital and PowerHouse Data Centers, would include data center facilities and on-site power generation. The agreement would allow the property to be annexed into Taylor and establish binding requirements related to noise, water use, setbacks, environmental protections and community investments.
The developers withdrew their annexation and zoning application last month, but continued negotiations with the city. Without an agreement, the project would have remained in unincorporated Williamson County, where the city would have had no authority over the development.
Under the proposed terms, the site would use a closed-loop cooling system with reclaimed water and an initial fill volume of 1.575 million gallons. Potable water generally would not be authorized for HVAC filling or evaporative cooling. The developers also would pay for utility connections, support wastewater infrastructure improvements and withdraw their Texas Commission on Environmental Quality wastewater discharge permit application.
The proposal includes setbacks and buffers near neighboring homes. Buildings would be at least 300 feet from the north, east and west property lines. Along the south property line near FM 112, data centers, power generation facilities and battery storage would be at least 700 feet away, with a permanent landscaped buffer of at least 400 feet and earthen berms at least 6 feet high.
An acoustic study would establish pre-development noise levels, with development noise limited to the greater of 65 dBA or that baseline. Lighting would also have to meet Taylor’s Dark Skies requirements.
The developers have committed $28.2 million for community investments and nonprofit support, including funding for city quality-of-life improvements, Taylor ISD programs, scholarships, workforce development, animal care and local nonprofit organizations.
The project is projected to generate $1.38 billion in gross tax revenue over 20 years. The developers are not seeking tax abatements.